Gypsum Powder Making Line Equipment with High Capacity
1.Production line type
1)Controlling part: Full Automatic
2)Annual capacity: 20,000 t~300,000t
3) Fuel: Natural gas, coal, diesel, heavy oil
4)Raw material: Natural gypsum rock (if adding some equipments, industrial by-product--desulfurization gypsum can be used), and in conformity with requirement of gypsum rock of over Grade 3 for making cementing material in JC/T 700-1998: Content of CaSO4·2H2O in raw material >70%.
2.Main Economical and Technical Parameter
3. Quality Standard:
Gypsum Powder Quality Standard: GB/T 9776-2008
Gypsum Powder: 80-100mesh
Composition: Content of β-CaSO4·1/2H2O (mass fraction) in calcined gypsum should be not less than 75%.
The Initial Setting Time: Shall Not Be Less Than 6 Minutes,
The Final Setting Time: Shall Not Be More Than 30 Minutes
4. Main Process
Gypsum Powder Plant(Nature Gypsum Rock)
Gypsum Mine -0-210mm gypsum rock→ Crushing →bucket elevator →silo → Raymond mill →screw conveyor → bucket elevator →material stablization silo →electronic belt scale →bucket elevator →boiling kiln →bucket elevator →FU chain conveyor →clinker silo →packing
5.Main production equipment introduction
Grinding systemAutomatic measuring systemCalcining systemOrganic heat carrier boilerAging &packing systemAutomatic control system
among them,the Gypsum powder ebullition furnace used in the calcining system has following advantages:
a; Small volume, large capacity
b; Simple structure, un-damageable
c; Compact structure, less land occupation, good de-dusting effect
d; Less energy consumption
e; Convenient to operate, easy to control
f; Good product quality, relatively ideal calcined gypsum phase composition, stable physical properties
g; Low capital construction investment& operation cost
And the This furnace uses electric energy or chemical energy generated by solid, liquid or gaseous fuels as main heat source and heat conductive oil as heat transfer medium. It adopts pipeline to connect boiler and thermal equipment into closed system. It also adopts new saving type heating way--- adopting forced circulation to heat thermal equipment. Compared with other heating equipment, it has the following obvious advantages:
a; Under low working pressure, it can obtain higher heating temperature. As a result, equipment investment cost is reduced and safety factor is intensified.
b; Heat uniformly and stably, accurately control heating temperature to avoid part heating to heated product, effectively improving product quality.
c; The heat conductive oil has no corrosion and scale, so investment for water treatment equipment which is necessary for heat transfer medium such as water or steam and pharmaceutical treatment cost is reduced.
d; The freezing point of heat conductive oil is relatively low and can be used in cold winter. Even if it is solidified, there is no expansion and no danger for cracking equipment.
e; One organic heat carrier boiler can supply heat for several users simultaneously with different temperatures. Thus the equipment investment for many heating equipments for many users is reduced.
f; Compared with steam boiler, organic heat carrier furnace can save over 40% energy, for it adopts liquid transmission to transfer energy, and circulated heating, without condensation emission to loss heat. It is the ideal energy-saving and environment-protecting products, easy to operate, safe and reliable.
1.Production line type
1)Controlling part: Full Automatic
2)Annual capacity: 20,000 t~300,000t
3) Fuel: Natural gas, coal, diesel, heavy oil
4)Raw material: Natural gypsum rock (if adding some equipments, industrial by-product--desulfurization gypsum can be used), and in conformity with requirement of gypsum rock of over Grade 3 for making cementing material in JC/T 700-1998: Content of CaSO4·2H2O in raw material >70%.
2.Main Economical and Technical Parameter
No | Name | Unit | Index |
1 | Annual capacity | MT | 30000 |
2 | Annual gypsum rock consumption | MT | 35000 |
3 | Working days/year | Day | 300 |
4 | Daily capacity | MT | 100 |
5 | Electricity consumption for producing one ton of gypsum powder | KWH | 30 |
6 | Coal (7000 kcal/kg) | Kg/t | 33 |
7 | Worker/shift | persons/shift | 6-7 |
8 | Controlling Part | Full Automatic | |
9 | Annual capacity | 20, 000-200, 000 Tons Per Year | |
10 | Calcining system | Ebullition furnace | |
Rotary kiln | |||
Rotary kiln | |||
11 | Fuel | Natural gas, diesel, coal, heavy oil | |
12 | Raw material | Natural Gypsum Rock | |
13 | Finished powder usage | Gypsum board | |
Plaster wall/Putty |
3. Quality Standard:
Gypsum Powder Quality Standard: GB/T 9776-2008
Gypsum Powder: 80-100mesh
Composition: Content of β-CaSO4·1/2H2O (mass fraction) in calcined gypsum should be not less than 75%.
The Initial Setting Time: Shall Not Be Less Than 6 Minutes,
The Final Setting Time: Shall Not Be More Than 30 Minutes
4. Main Process
Gypsum Powder Plant(Nature Gypsum Rock)
Gypsum Mine -0-210mm gypsum rock→ Crushing →bucket elevator →silo → Raymond mill →screw conveyor → bucket elevator →material stablization silo →electronic belt scale →bucket elevator →boiling kiln →bucket elevator →FU chain conveyor →clinker silo →packing
5.Main production equipment introduction
Grinding systemAutomatic measuring systemCalcining systemOrganic heat carrier boilerAging &packing systemAutomatic control system
among them,the Gypsum powder ebullition furnace used in the calcining system has following advantages:
a; Small volume, large capacity
b; Simple structure, un-damageable
c; Compact structure, less land occupation, good de-dusting effect
d; Less energy consumption
e; Convenient to operate, easy to control
f; Good product quality, relatively ideal calcined gypsum phase composition, stable physical properties
g; Low capital construction investment& operation cost
And the This furnace uses electric energy or chemical energy generated by solid, liquid or gaseous fuels as main heat source and heat conductive oil as heat transfer medium. It adopts pipeline to connect boiler and thermal equipment into closed system. It also adopts new saving type heating way--- adopting forced circulation to heat thermal equipment. Compared with other heating equipment, it has the following obvious advantages:
a; Under low working pressure, it can obtain higher heating temperature. As a result, equipment investment cost is reduced and safety factor is intensified.
b; Heat uniformly and stably, accurately control heating temperature to avoid part heating to heated product, effectively improving product quality.
c; The heat conductive oil has no corrosion and scale, so investment for water treatment equipment which is necessary for heat transfer medium such as water or steam and pharmaceutical treatment cost is reduced.
d; The freezing point of heat conductive oil is relatively low and can be used in cold winter. Even if it is solidified, there is no expansion and no danger for cracking equipment.
e; One organic heat carrier boiler can supply heat for several users simultaneously with different temperatures. Thus the equipment investment for many heating equipments for many users is reduced.
f; Compared with steam boiler, organic heat carrier furnace can save over 40% energy, for it adopts liquid transmission to transfer energy, and circulated heating, without condensation emission to loss heat. It is the ideal energy-saving and environment-protecting products, easy to operate, safe and reliable.